火力发电厂烟气脱硫系统中安装GGH的优劣分析
火力发电厂烟气脱硫系统中安装GGH的优劣分析
【摘要】目前火力发电厂烟气脱硫系统对吸收塔尾部净烟气的处理一般采用的两种方法:一是通过GGH(烟气换热器)对净烟气进行再热处理后进行排放;二是将烟囱设计为湿烟囱,直接排放净烟气。笔者曾先后担任过不同火力发电厂四台百万级燃煤发电机组的脱硫工程专业监理工程师,通过长期积累的实践经验结合自身的专业知识,对火力发电厂烟气脱硫系统中安装GGH的优劣进行一些简要的分析。
【关键词】
火电厂,脱硫,GGH ,优劣分析
【 abstract 】
At present thermal power plant flue gas desulfurization system of the absorber tail gas treatment generally USES the net of the two methods: one is through the GGH (flue gas heat exchanger) for net after heat treatment before the flue gas discharge; The other is the chimney design to wet the chimney, direct emissions net flue gas. The author has a different thermal power plant the four sets of a class of coal-fired generators desulfurization engineering supervision engineer, through the long-term accumulated experience with your own professional knowledge of thermal power plant flue gas desulfurization system installation GGH disadvantages of some brief analysis.
【 key words 】
The power plant, the desulfurization, GGH, quality analysis
【前言】
火力发电厂在生产过程中,伴随燃料的燃烧会产生大量的对环境有害的烟气,硫氧化物(SxOy)是烟气中主要的有害物质之一。随着国家对环境保护的日益重视,对火力发电厂烟气排放的控制指标也越来越严格,除尘、脱硫甚至是脱硝这些环保设施已经在国内的火力发电厂基本得到普及,GGH作为火力发电厂烟气脱硫系统中一个重要的设备也相应的得到了广泛的应用。但由于安装GGH后会出现烟气阻力增加、GGH检修频繁等问题,部分火电厂脱硫系统取消了GGH的安装,将经过吸收塔脱硫处理的净烟气直接通过烟囱排放。不过净烟气直接排放也会带来吸收塔入口烟温提高、工艺水消耗增加和地面污染物浓度增加等问题。本文将对火电厂烟气脱硫系统安装GGH的优劣进行分析比较,并提