碾压混凝土坝施工工艺应用
碾压混凝土坝施工工艺应用
摘要:碾压混凝土大坝具有工艺简单、上坝强度高、工期短、造价低、适应性强等特点,能产生较大的经济和环境效益,目前这种坝型在国内水利水电建设中已得到广泛应用。该文结合马堵山水电站工程碾压混凝土施工技术,比较全面地介绍了碾压混凝土坝施工工艺要点。
关键词: 水电站大坝施工,碾压混凝土 , 施工工艺
Abstract: RCC dam has the simple process, the intensity is high, the dam short time, low cost, strong adaptability and other characteristics, can produce larger economic and environmental benefits, the current in the domestic water conservancy and hydropower dam type construction has been widely used. Combining with the horse plugging landscape power engineering RCC construction technology, quite comprehensively introduces RCC dam construction process points.
Keywords: hydropower station dam construction, RCC, construction technology
http:///
一、工程概况
马堵山水电站位于红河干流下游红河州的个旧市、金平县境内,是红河干流三江口以下规划的12个梯级的第10个梯级。电站枢纽主要建筑物由拦河坝、泄洪表孔及泄洪底孔、电站进水口、有压引水隧洞、地面厂房及开关站等组成。枢纽坝轴线呈折线布置,为碾压混凝土重力坝,沿坝线共分15个坝段,坝顶总长352.957m,最大坝高107.5m。砼总方量为91.8万m3,其中碾压砼方量为60.7万m3。
二、碾压混凝土坝的主要特点
1、使用大型施工机械设备,运输、平仓、振实、切缝等施工使用自卸汽车、推土机、振动碾、割缝机等机械化施工,实现快速、大仓面碾压施工。
2、相比较常态混凝土水泥用量少,大量使用粉煤灰或天然火山灰等掺和料,掺量占胶凝材料总量的30%~60%,单价可以降低15%左右;同时因为大仓面施工,还可以节约模板工程量,可节约模板费用30%左右,混凝土运输可用自卸汽车运输,比混凝土搅拌车运输费用可节约40%左右,造价低的优势显而易见。
三、碾压混凝土坝施工
1、碾压混凝土试验